PERMIT �) DDRESS: JOB CODE:
Rough Inspection continued
g p
Date
Inspector
Initials
Comments
316 Rough Mechanical Residential
317 Rough Mechanical Commercial
t
318 Boiler/ Furnace
319 Hot water tank
320 Drywall screw and Nail
321 Moisture board / shower walls
407 Final Plumbing Residential
322 Rough Grading
408 Final Plumbing Commercial
323 Miscellaneous
409 Final Roof
Final Inspections
Date
Inspector
Initials
Comments
402 Gas Meter Release
403 Final Electrical Residential
t
404 Final Electrical Commercial
405 Final Mechanical Residential
406 Final Mechanical CommercialrQm
Kk",140\64
407 Final Plumbing Residential
408 Final Plumbing Commercial
409 Final Roof
410 Final Window/Door
411 Landscape/Park/Planning*
Inspections from these entities shall be requested
one week in advance.
*For landscaping and parking inspections please
call 303-235-2846
**For ROW and drainage inspections please call
303-235-2861
***For fire inspections please contact the Fire
Protection District for your project.
412 Row/Drainage/Public Works**
413 Flood plain Inspection**
414 Fire Insp. / Fire Protection***
415 Public Works Final**
416 Storm Water Mgmt.**
417 Zoning Final Inspection*
418 Building Final Inspection
Note: All items must be completed and approved by Planning, Public Works, Fire and Building
before a Certificate of Occupancy is issued. Approval of the Final Building Inspection does not
constitute authorization of occupancy.
For Low Voltage permits please be sure that rough inspections are completed by the Fire District and
Electrical low voltage by the Building Division.
INSPECTION RECORD
Inspection online form: http://www.ci.wheatridge.co.us/inspection
Cancellations must be submitted via the online form before 8 a.m. the day of the inspection
Inspections will not be performed unless this card is posted on the project site
Request an inspection before MIDNIGHT (11:59 P to receive n inspection following business da
�/ /� ADDRESS: ,�2 JOB CODE:
PERK -1 — - /C
Foundation Inspections
Date
Inspector
Initials
Comments
102 Caissons / Piers
103 Footing / P.E. Letter
104 Foundation Setback Cert.
105 Stem Walls
106 Foundation wall Insulation
,
Do Not Pour Concrete Prior To Approval Of The Above Inspections
Underground 1 Slab Inspections
Date
Inspector
Initials
Comments
201 Electrical / Cable/ Conduit
202 Sewer Underground Int.
203 Sewer Underground Ext.
204 Plumbing Underground Int.
205 Plumbing Underground Ext.
,
206 Water Underground
Do Not Cover Underground or Below / In -Slab Work Prior To Approval Of The Above Inspections
Rough Inspection
Date
Inspector
Initials
Comments
301 Rough Framing
302 Wall Sheathing
303 Roof Sheathing
304 Sheer Inspection
305 Insulation
,
306 Mid -Roof
307 Metal / Lath / Stucco
308 Rough Electrical Residential
309 Rough Electrical Commercial
310 Electrical Meter Residential
311 Electrical Meter Commercial
312 Temp. Const. Meter
313 Rough Plumbing Residential
314 Rough Plumbing Commercial
315 Shower Pan
SEE OVER FOR ADDITIONAL INSPECTIONS
C
-63
The City of Wheat Ridge
Inspection Check List notes
Final Roof
Notes
Company Name:
Inspector signature:
Date of Inspection: �, —
The City of Wheat Ridge
Inspection Check List notes
Final Roof
Roof Inspection
❑ N/A
❑ Pass
❑ Fail
❑ N/A
��ass
E] Fail
Structural roof components
❑ N/A
ass
❑ Fail
Verify that no more than 2 layers of shingles exist
❑ N/A
❑ Pass
❑ Fail
Flashing for roof and walls
❑ Pass
❑ Fail
If new sheathing is installed verify that it is listed in the
permit description (Valuation must be adjusted)
�-
ETN/A
❑ Pass
❑ Fail
Verify sheathing nail pattern (See Policy & Procedures)
.D N/A
❑ Pass
❑ Fail
Crickets and saddles where needed
❑ N/A
ass
❑ Fail
Verify B vent must have boot same gauge as pipe
❑ N/A
—0 Pass
[] Fail
Verify vent caps
❑ N/A
-0Pass
❑ Fail
Verify no flashings are damaged or rusted
❑ N/A
.0 Pass
❑ Fail
Step flashing shall be min. of 4x4 piece per shingle
E N/A
❑ Pass
❑ Fail
Verify scuppers allow for proper drainage
❑ N/A
ass
❑ Fail
Ice and water shield 2' in heated wall spaces
❑ N/AP
ss
El Fail
Underlayments must follow 2012 IRC / 2012 IBC
❑ N/A
ss
ET
❑ Fail
Verify roof slope for proper drainage
❑ N/A
Pass
❑ Fail
Dripedge shall have min of 2" overlap
❑ N/A
❑ Pass
❑ Fail
Dripedge should extend down min 2" past roof deck
❑ N/A
Pass
❑ Fail
Dripedge shall be mechanicaly fastened 12" OC
[D'N/A
❑ Pass
❑ Fail
90 LB roll roofing shall not be applied to roof slopes
less than 2:12 slope; Exception: detached garages,
patios, carports, open on three sides with min. slope of
1:12
N/A
❑ Pass
❑ Fail
Modified Bitumen, EPDM, TPO min slope 1/4:12 slope
N/A
❑ Pass
❑ Fail
Above roof insulation R-25
N/A
❑ Pass
❑ Fail
Below roof residential R-38
N/A
❑ Pass
❑ Fail
Below roof commercial R-32
N/A
❑ Pass
❑ Fail
Modified Bitumen, EPDM, TPO min slope 1/4:12 slope
must be installed in accordance with the manufacturer's
specifications - Must have manufacturer's letter of
warranty with the address on the letter for final inspection
Metal Roof Shingles Requirements
N/A
❑ Pass
❑ Fail
Metal roof shingles shall not be installed on slope less
3:12
N/A
❑ Pass
❑ Fail
Metal valley flashing shall be the same material as roof
N/A
❑ Pass
❑ Fail
Metal valley flashing shall extend a min of 8" from the
centerline with a min. of 3/4 " high splash diverter
rib built-in at the flow line with sections overlapping a
a min. of 4"
dN/A
Tile Roofs Requirements
❑
Pass
❑ Fail
Clay and concrete tile shall have a min. 2-1/2:12 slope
Slopes 4:12 and under require double underlayment
0 ;4�)42 .L.,)
The City of Wheat Ridge
Inspection Check List notes
Mid -Roof
Notes
�cr Z2 fi
cz v C,
—12 to Lt:._� � _ L_ � �- — (- L v2 ,1 i l 4 --
Company Name: it._ ��� 4 ��C.,. C—
Inspector signature:
Date of Inspection:
Roof Insaection
❑ N/A
❑ Pass
❑ Fail
❑ N/A
ff Pass
❑ Fail
❑ N/A
'10 -Pass
❑ Fail
N/A
t0-
,�I Pass
❑ Fail
❑ Pass
❑ Fail
�N/A
,� '— 1A
❑ N/A
❑ N/A
❑ N/A
�,�❑ NIA
J" NA
❑ N/A
❑ N/A
❑ N/A
❑ N/A
❑ N/A
N/A
N/A
N/A
N/A
N/A
N/A
N/A
N/A
N/A
❑ Pass
❑ Pass
ZI—Pass
EFPass
Pass
Er Pass
❑ ss
Pass
Pass
Pass
Pass
Pass
Pass
❑ Pass
i
Pass
Pass
Pass
Pass
Pass
❑ Fail
❑ Fail
❑ Fail
❑ Fail
❑ Fail
❑ Fail
❑ Fail
❑ Fail
❑ Fail
❑ Fail
❑ Fail
❑ Fail
❑ Fail
❑ Fail
❑ Fail
❑ Fail
❑ Fail
❑ Fail
❑ Fail
The City of Wheat Ridge
Inspection Check List notes
Mid -Roof
Structural roof components
Verify that no more than 2 layers of shingles exist
Flashing for roof and walls
If new sheathing is installed verify that it is listed in the
permit description (Valuation must be adjusted)
Verify sheathing nail pattern (See Policy & Procedures)
Crickets and saddles where needed
Verify B vent must have boot same gauge as pipe
Verify vent caps
Verify no flashings are damaged or rusted
Step flashing shall be min. of 4x4 piece per shingle
Verify scuppers allow for proper drainage
Ice and water shield 2' in heated wall spaces
Underlayments must follow 2012 IRC / 2012 IBC
Verify roof slope for proper drainage
Dripedge shall have min of 2" overlap
Dripedge should extend down min 2" past roof deck
Dripedge shall be mechanicaly fastened 12" OC
90 LB roll roofing shall not be applied to roof slopes
less than 2:12 slope: Exception, detached garages,
patios, carports, open on three sides with min. slope of
1:12
Modified Bitumen, EPDM, TPO min slope 1/4:12 slope
Above roof insulation R-25
Below roof residential R-38
Below roof commercial R-32
Modified Bitumen, EPDM, TPO min slope 1/4:12 slope
must be installed in accordance with the manufacturers
specifications- Must have manufactures letter of
warranty with the address on the letter for final inspection
Metal Roof Shingles Requirements
❑ Pass ❑ Fail Metal roof shingles shall not be installed 011 slope less
3:12
❑ Pass ❑ Fail Metal valley flashing shall be the same material as roof
❑ Pass ❑ Fail Metal valley flashing shall extend a min of 8" from the
centerline with a min. of 3/4 " high splash diverter
rib built-in at the flow line with sections overlapping a
a min. of 4"
_Tile Roofs Requirements
❑ Pass ❑ Fail Clay and concrete the shall have a min. 2-1/2:12 slope
Slopes 4:12 and under require double underlayment
The City of Wheat Ridge
Third_ Party Form Check List
Property Address 3
Permit Number 'qo/ 70 70
Permit Issued Date j A - �4 — f
Owner Information _
Property Owner Information -
Property Owner Address
Inspector Information
Inspection Company 'V41 u a, — LC' �e j I _
Inspector Name '12 y j lc r ,yl .L -fc -I
Inspector Contact info. _ (& Q i__1 :2
Inspector Statement and Acknowledgement
* I hearby acknowledge the roof I am inspecting is 6/12 or over. All roofs
that are under 6/12 must be inspected by the City of Wheat Ridge Buiding Dept.
* I hearby acknowledge the roofing system for the referenced building has been inspected
and found to be in compliance with the minimum requirements of the 2012 IRC and 2012
IBC as well as all City of Wheat Ridge Policies and Procedure and Manufacturer's
recommendations and specifications.
Inspector: % ` e, r at � "rte t Date: / - 1 %
Property Owner Statement of Acknowledgement
*1 hearby acknowledge that I am the owner of the building referenced above and I give
my consent for the listed third -party inspection company to perform my roof inspection
in lieu of the City of Wheat RVgSeAuildin
sion ' sp ction.
Pro a Owner/Agent: ent:
pry 9 _ Date: - —;
This original document and permit c , a ell as the roofing check list, must be submitted tc
the Chief Building Official within seven' ays of the final inspection.
Drop off in person
Permit counter 2nd floor
7500 W. 29th Ave
Wheat Ridge CO 80033
Draft Date: 7/26/17
Please add note to reverse side