Loading...
HomeMy WebLinkAboutResolution 26, 2021CITY OF WHEAT RIDGE, COLORADO RESOLUTION NO. 26 Series of 2021 TITLE: A RESOLUTION AMENDING THE FISCAL YEAR 2021 CAPITAL IMPROVEMENT PROGRAM BUDGET TO REFLECT THE APPROVAL OF A SUPPLEMENTAL BUDGET APPROPRIATION FOR THE PURPOSE OF AWARDING A CONTRACT AMENDMENT AND SUBSEQUENT PAYMENTS TO SHORT ELLIOT HENDRICKSON, INC., DENVER, CO, IN AN AMOUNT NOT TO EXCEED $160,563.36 FOR PROFESSIONAL SERVICES TO COMPLETE THE CONSTRUCTION PLANS AND SPECIFICATIONS FOR WHEAT RIDGE WARD STATION STREET IMPROVEMENTS WHEREAS, the council recognizes the importance and significance of restarting the construction plans and specifications for Wheat Ridge Ward Station street improvements; and WHEREAS, insufficient appropriations in the 2021 Budget exist to cover these expenditures; and WHEREAS, the City will receive funds from the City of Arvada as reimbursement for design and right-of-way consulting services for projects in the Wheat Ridge · Ward Station area; and WHEREAS, the Wheat Ridge Charter requires that amendments to the budget be effected by the City Council adopting a resolution. NOW, THEREFORE, BE IT RESOLVED by the Wheat Ridge City Council, that: Section 1. A transfer of $160,563.36 is hereby approved from the Capital Improvement Project budget undesignated reserves to account 30-303-800-860 and the 2021 revenues are amended accordingly. Section 2. A contract amendment of $160,563.36 is hereby approved to complete the construction plans and specifications for 52nd Avenue, Tabor Street, Ridge Road, and the 52nd Avenue and Ward Road intersection. DONE AND RESOLVED this 10th day of May 2021. Bud Starker, Mayor ATTEST: Steve Kirkpatrick, City Clerk